Construction job margin calculator

A lot of contractors find out what a job made after it closes. Enter what you bid, what you have spent and how far along the job is, and see where the margin is heading while there is still time to act.

The bid

Add them even if they are not billed yet.

From your bid: labor, materials, subcontractors and equipment, including the cost of approved change orders.

The job so far

Everything posted to the job to date.

Your best measure of how much of the work is done.

Example figures are filled in. Replace them with yours. Nothing you type is saved or sent anywhere.

Your numbers

Turn on JavaScript to see the results here. The formulas are below if you would rather work it out by hand.

How it is worked out

Bid margin = (contract + change orders − estimated cost) ÷ (contract + change orders)

If the rest goes to the estimate: final cost = cost so far + estimated cost × (1 − percent complete)

If the rest goes the way it has so far: final cost = cost so far ÷ percent complete

A $112,000 job with $8,000 in approved change orders, estimated at $84,000, was bid at a 30.0% margin. At 60% complete it has cost $57,600, against the $50,400 the estimate allows at this point: $7,200 over. If the rest goes to the estimate, it finishes at 24.0%. If it keeps going the way it has, it finishes at 20.0%, up to 10 points below the bid. The truth is usually somewhere between the two.

What a good number looks like

There is no single right margin. It depends on your trade, your market and your overhead. The number that matters is your own bid margin, and how far each open job has drifted from it.

Questions

Why does a job's margin drop while it is running?

Labor running over the estimate is the usual cause, then material prices and change orders nobody priced or billed. Each one is small on the day and adds up by the end.

How do I measure percent complete?

Use what fits the job: the share of estimated labor hours used, milestones reached or units installed. Measure it the same way every week. A guess that is too hopeful hides an overrun.

What is margin fade?

The drop from the margin a job was bid at to the margin it actually earns. Watching it while the job is open is how you catch it in time.